P-29

Playground Rennovation

Description

Financing

Documents

Photos

History Logs

Project Description

Country: USA

Location: Fallbrook CA

Total Budget: $8,000

Areas of Focus: Maternal and child health, Basic education and literacy, Economic and community development

Activity Type: Community Development: General

Summary: Renovate the playground equipment at La Paloma Elementary School in Fallbrook, CA


The playground equipment at La Paloma Elementary School is used seven days a week by students, youth sports groups, after school programs and the general public. The equipment is worn and loose and wood fiber cushioning beneath the equipment has disappeared. The school principal and assistant principal have identified rennovation of this equipment as a high priority that they lack funds to complete. This project would repair / replace worn chin up bars and swing set, rebuild fiber cushioning pits beneath the equipment and replace missing wood chips.

The rennovated equipment will create a safer, more attractive campus and encourage, stronger, healthier children. Healthier children miss fewer days of school due to illness, improve their concentration in the classroom and progress in their schoolwork. More children succeeding in their school studies will be reflected in improved test scores and grades and reflect well on the school as well as the entire school district.

The Fallbrook Village Rotary Club is willing to step in and support the needs of the school district in these times of budget reductions demonstrates a strong community support for the school district.

A strong school district makes the community a more attractive place for families with children to live, rent or buy homes, and purchase clothing, food and services in support of the local economy.

Project Contact Person

District: 5340

Rotary Club of: Fallbrook Village

Primary Contact: Gordon Stone

Email: gordon.stone@sdcounty.ca.gov

Project Status

Completed
This project is "Completed". This means the project has been implemented and the report was accepted by the district leadership. The project will stay listed on this website as a testimony of the achievements of the project partners.

Project listed for the 2010-11 Rotary Year.

Proposed Financing

Existing Contributions Towards This Project

Date

Cash

DDF

Total

Fallbrook Village (5340)

28-Apr-10

$4,000

$4,000

$8,000

Total

$4,000

$4,000

$8,000

Project Supporting Documents


[6-Jul-10]


[29-Apr-10]
Grant - P-29


[6-Jul-10]
La Paloma Playground Specs 2


[6-Jul-10]
Letter from La Paloma Principal


[9-Feb-11]
P29-La Paloma


[9-Feb-11]
P29-La Paloma

 

Project Photos

Under Construction 1

Plaque

History Log Entries

28-Apr-10

System Entry

Creation of project page.

30-Apr-10

System Entry

Project sent for club signatures.

30-Apr-10

System Entry

Project sent for club signatures.

30-Apr-10

System Entry

Project sent for club signatures.

30-Apr-10

System Entry

Project signed by Gordon Stone.

30-Apr-10

System Entry

Project signed by Gordon Stone.

30-Apr-10

System Entry

Project signed by Scott Harry.

30-Apr-10

System Entry

Project signed by Scott Harry.

30-Apr-10

System Entry

Project signed by Steve Achard.

30-Apr-10

System Entry

Project signed by Gordon Stone.

3-May-10

System Entry

Project approved by the District Approval Committee

19-Sep-10

System Entry

Check for DDF payment issued by Foundation Treasurer.

9-Feb-11

by Steve Achard

Final total cost of project. Project finished.

9-Feb-11

by Steve Achard

Total cost of play ground equipment for La Paloma - P29

9-Feb-11

System Entry

Project has been implemented and final report uploaded.

9-Feb-11

System Entry

Final report approved by the District Approval Committee.