P-3855

Santa Maria Reservoir

Description

Financing

Documents

Photos

History Logs

Project Description

Country: Mexico

Location: Colon

Total Budget: $62,774

Area of Focus: Water, sanitation and hygiene

Activity Type: Water: Supply/Access

Summary: Reservoir for irrigation of agricultural field


Santa Maria Orphanage is located in Colon Mexico (Central Mexico). The orphanage has about 300 orphans from 2 to 18 in age, both girls and boys. This project will allow them to irrigate their farm on the property more consistently over a year. The reservoir will also increase their irrigation acreage by 30 to 40 acres (from 30 acres currently to 70 acres in total). This will allow for the planting of alfalfa for the dairy cow operation as well as for corn as a food resource for both the animals on the farm as well as the children at the orphanage.


Addendum to Project Description (added after the project was signed)

Jan 23, 2024 - This project is complete. I am in the process of providing the final accounting and engineering reports. I will have this completed by the end of the month (Jan 2024).

Project Contact Person

District: 5440

Rotary Club of: Fort Collins

Primary Contact: David Stewart

Email: dave.stewart@stewartenv.com

Project Status

Completed
This project is "Completed". This means the project has been implemented and the report was accepted by the district leadership. The project will stay listed on this website as a testimony of the achievements of the project partners.

Project listed for the 2021-22 Rotary Year.

Proposed Financing

Existing Contributions Towards This Project

Date

Cash

DDF

Total

Fort Collins (5440)

22-May-21

$5,000

$5,000

$10,000

Queretaro (4140)

22-May-21

$3,000

$3,000

$6,000

Logan (5420)

22-May-21

$1,000

$0

$1,000

Loveland (5440)

22-May-21

$1,000

$0

$1,000

Fort Collins (5440)

22-May-21

$500

$0

$500

Fallbrook (5340)

22-May-21

$4,887

$0

$4,887

Fort Collins (5440)

22-May-21

$39,387

$0

$39,387

Total

$54,774

$8,000

$62,774

Project Supporting Documents

Project Photos

History Log Entries

22-May-21

by David Stewart

We have converted the Global Grant request to a District Grant request due to issues with the community assessment part of the Global Grant process. This grant is fully funded and should be started this summer (after July 1, 2021).

22-May-21

by David Stewart

System Entry: Creation of project page.

22-May-21

by David Stewart

System Entry: Pledge of $3,000 with $3,000 DDF by Jose Puon of the Rotary Club of Queretaro, District 4140.

22-May-21

by David Stewart

System Entry: Pledge of $1,000 by Mark Hargrave of the Rotary Club of Logan, District 5420.

22-May-21

by David Stewart

System Entry: Pledge of $1,000 by Jim Epstien of the Rotary Club of Loveland, District 5440.

22-May-21

by David Stewart

System Entry: Pledge of $500 by Dave Stewart of the Rotary Club of Fort Collins, District 5440.

22-May-21

by David Stewart

System Entry: Pledge of $4,887 by Tina Lanfham-Smith of the Rotary Club of Fallbrook, District 5340.

22-May-21

by David Stewart

System Entry: Pledge of $39,387 by Dave Stewart of the Rotary Club of Fort Collins, District 5440.

2-Jun-21

by David Stewart

System Entry: Project sent for club signatures.

2-Jun-21

by David Stewart

System Entry: Project signed by Dave Stewart.

2-Jun-21

by John Trone

System Entry: Project signed by John Trone.

7-Jun-21

by Randall Looper

Dave & John,

The report that was loaded does not include a budget of income and expenses for this project. Can create a basic budget and upload.

12-Aug-21

by Janice Kurth

System Entry: Signature Process cancelled by user.

20-Sep-21

by John Trone

System Entry: Project sent for club signatures.

20-Sep-21

by John Trone

System Entry: Project signed by John Trone.

24-Sep-21

System Entry

System Entry: Project signed by Dave Stewart.

24-Sep-21

by Randall Looper

System Entry: Project approved by the District Approval Committee.

27-Sep-21

by Bill Kehl

System Entry: Check for DDF payment issued by Foundation Treasurer.

28-Sep-21

by Randall Looper

Dave,

The check for the grant has been mailed. Please let me know when you have received it.

Randy

15-Oct-21

by John Trone

Check has been received by Club.

18-Oct-21

by Randall Looper

System Entry: Project has been implemented and final report uploaded.

2-Nov-21

by Randall Looper

System Entry: Project reverted to "Paid".

8-Apr-22

by Randall Looper

Dave,

Please provide a quarterly history log update as to the status of this project.

Randy

9-Jun-22

by David Stewart

A contractor has been retained and started work. The Queretaro Rotary club is setting up an account to accept funds. All funds have been raised. A final inspection of the work is anticipated at the beginning of July 2022. A final report will follow.

15-Sep-22

by Randall Looper

David

Please provide a quarterly history log update as to the status of this project.

9-Jan-23

by Randall Looper

David,

Please provide a quarterly history log update as to the status of this project.

12-Apr-23

by Randall Looper

David,

Please provide a quarterly history log update as to the status of this project.

The grant will be over 2 years old in September 23 at which time the grant needs to be closed out.

Randy

12-Jul-23

by Randall Looper

David,

Please provide a quarterly history log update as to the status of this project.

Randy

26-Jul-23

by David Stewart

This project is 95% complete. We have a final engineering report due and then I will finish the project report to Rotary. I would estimate that I will have a final report in this quarter.

14-Oct-23

by Randall Looper

David,

Have you received the engineering report yet?

15-Jan-24

by Randall Looper

David,

Please provide a quarterly history log update as to the status of this project.

23-Jan-24

by David Stewart

This project is complete. I am in the process of completing the final report on the District form. I should have this by the end of the month. Dave Stewart

8-May-24

by Randall Looper

Dave,

I just wanted to remind you that you need to have the receipts and the final report uploaded to the documents area before June 7th if the Fort Collins club wants to apply for a district grant for the 24-25 Rotary year.

Randy

15-May-24

by David Stewart

Project is complete. The inspection by the engineer was completed a few weeks ago. There are still some minor issues of covering the liner with soil that will be completed in the fall when the water goes down. I will provide a full report by the end of May 2024.

1-Jun-24

by David Stewart

Final Report for Santa Maria is uploaded to the site. Additional photos will be added.

4-Jun-24

by Randall Looper

System Entry: Project has been implemented and final report uploaded.

4-Jun-24

by Randall Looper

System Entry: Final report approved by the District Approval Committee.