18-May-22 |
by Marianne Barker |
System Entry: Creation of project page.
|
18-May-22 |
by Marianne Barker |
System Entry: Project sent for club signatures.
|
18-May-22 |
by Marianne Barker |
System Entry: Project signed by Marianne Barker.
|
23-May-22 |
System Entry |
System Entry: Project signed by Jim Hogge.
|
1-Aug-22 |
by Marianne Barker |
System Entry: Project approved by the District Approval Committee.
|
16-Aug-22 |
by Marianne Barker |
System Entry: Check for DDF payment issued by Foundation Treasurer.
|
30-Dec-22 |
by Marianne Barker |
System Entry: Project has been implemented and final report uploaded.
|
6-Jan-23 |
by Bob Rose |
I have audited this project and I approve it.
|
7-Jan-23 |
by Marianne Barker |
System Entry: Final report approved by the District Approval Committee.
|