19-May-22 |
System Entry |
System Entry: Creation of project page.
|
1-Jun-22 |
by Lee Van Slyke |
System Entry: Project sent for club signatures.
|
1-Jun-22 |
by Lee Van Slyke |
System Entry: Project signed by Oakley Van Slyke.
|
2-Jun-22 |
by Tyler Boden |
System Entry: Project reverted to "Submitted" - Tyler Boden added to the list of signatories.
|
2-Jun-22 |
by Tyler Boden |
System Entry: Project signed by Tyler Boden.
|
5-Aug-22 |
by Helen Maxwell |
System Entry: Project approved by the District Approval Committee.
|
16-Aug-22 |
by Helen Maxwell |
System Entry: Check for DDF payment issued by Foundation Treasurer.
|
2-May-23 |
by Tyler Boden |
System Entry: Project has been implemented and final report uploaded.
|
13-May-23 |
by Lee Van Slyke |
The PTA has the funds to buy the garden signs. The remaining steps are to receive the signs for the garden and install them, which is scheduled for May 27. Five Rotarians have volunteered.
|
17-May-23 |
by Helen Maxwell |
System Entry: Project reverted to "Paid".
|
2-Jul-23 |
by Helen Maxwell |
System Entry: Project has been implemented and final report uploaded.
|
2-Jul-23 |
by Helen Maxwell |
System Entry: Final report approved by the District Approval Committee.
|