8-May-23 |
by Don LaBarge |
System Entry: Creation of project page.
|
9-May-23 |
by Rebecca Wilks |
Thank you for your application. In order to complete club qualification, you must submit the signed MOU.
|
10-May-23 |
by Don LaBarge |
System Entry: Project sent for club signatures.
|
10-May-23 |
by Don LaBarge |
System Entry: Project signed by Don LaBarge.
|
10-May-23 |
by Colleen Coons |
System Entry: Project signed by Colleen Coons.
|
19-May-23 |
by Rebecca Wilks |
I've backed out of the signature process because I was not included. We'll all need to sign it again.
|
19-May-23 |
by Rebecca Wilks |
System Entry: Signature Process cancelled by user.
|
19-May-23 |
by Rebecca Wilks |
System Entry: Project sent for club signatures.
|
19-May-23 |
by Rebecca Wilks |
System Entry: Project signed by Rebecca Wilks.
|
19-May-23 |
by Don LaBarge |
System Entry: Project signed by Don LaBarge.
|
19-May-23 |
System Entry |
System Entry: Project signed by Colleen Coons.
|
16-Jun-23 |
by Rebecca Wilks |
Congratulations! This project has been approved for full funding. We need to do some administrative things, so we don’t know exactly when the money will hit your account, but our best guess is a month or so. We’ll send you an update when we have one. Please also remember that you may not spend money prior to TRF approval and reimburse yourself from grant funds. If there have been changes in your bank account (information for electronic transfer), please get that to Lucinda General (District Treasurer) as soon as possible. treasurer@rotary5495.org. Your report is due April 30, 2024, and receipts are required to complete the report (not invoices, cancelled checks, UPS shipping labels, or any other documents). Thank you for making the world a better place.
|
16-Jun-23 |
by Rebecca Wilks |
System Entry: Project approved by the District Approval Committee.
|
7-Aug-23 |
by Caleb Lowe |
Your District Grant has been approved by The Rotary Foundation We expect electronic payments will be initiated before Friday August 11. You may begin making project expenditures now. If there have been changes in your bank account (information for electronic transfer), please get those to Lucinda General (District Treasurer) as soon as possible. treasurer@rotary5495.org. Your report is due April 30, 2024, and receipts are required to complete the report (not invoices, cancelled checks, UPS shipping labels, or any other documents). Thank you again for your good work.
|
8-Aug-23 |
by Caleb Lowe |
System Entry: Check for DDF payment issued by Foundation Treasurer.
|
10-Mar-24 |
by Rebecca Wilks |
A friendly reminder: Your completed, signed report form, along with receipts for all project expenditures must be uploaded to this page by April 30. The report form can be found here: https://portal.clubrunner.ca/50335/Documents/en-ca/da933040-cc9e-4230-b2e6-2a5900705ea4/1/
|
14-Apr-24 |
by Rebecca Wilks |
Just one last reminder you have about two weeks to complete the report for this grant and submit it with all project receipts. Thanks. https://portal.clubrunner.ca/50335/Documents/en-ca/da933040-cc9e-4230-b2e6-2a5900705ea4/1/
|
19-Apr-24 |
by Colleen Coons |
Mesa West Rotary has completed P-4697, Westwood HS Working Warriors program. This project will continue, as changes in the space has delayed set up of the DC. Product will be stored at Mesa Public Schools until teacher Daniel Becker receives more space. That said the equipment purchased has provided value and efficiency to his program which will continue.
|
19-Apr-24 |
by Rebecca Wilks |
Thank for uploading receipts. I don't see the completed report form.
|
19-Apr-24 |
by Colleen Coons |
Rebecca: I have uploaded the PDF _4697 Westwood HS Working Warriors. I believe this is the document you are looking for? Let me know.
|
21-Apr-24 |
by Rebecca Wilks |
System Entry: Project has been implemented and final report uploaded.
|
21-Apr-24 |
by Rebecca Wilks |
System Entry: Final report approved by the District Approval Committee.
|