18-Dec-23 |
by Kim McDowell |
Submitted project with budget and documents.
|
18-Dec-23 |
by Kim McDowell |
System Entry: Creation of project page.
|
18-Dec-23 |
by Kim McDowell |
System Entry: Project sent for club signatures.
|
18-Dec-23 |
by Kim McDowell |
System Entry: Project signed by Jon McDowell.
|
20-Dec-23 |
by Kim McDowell |
Finalized local signatures.
|
20-Dec-23 |
by Kim McDowell |
System Entry: Project signed by Kim McDowell.
|
22-Dec-23 |
by Kim McDowell |
Added two additional school flyer documents.
|
5-Jan-24 |
by Kim McDowell |
System Entry: Project reverted to "Submitted" - Chris Woodruff added to the list of signatories.
|
15-Jan-24 |
by Randall Looper |
System Entry: Project approved by the District Approval Committee.
|
15-Jan-24 |
by Randall Looper |
System Entry: Check for DDF payment issued by Foundation Treasurer.
|
3-Feb-24 |
by Jon McDowell |
Grant Payment check for $1000.00 received 01/30/24.
Four bikes and helmets purchased on 02/01/24 for $740.31 and given out at southside Elementary school assembly on 02/02/24.
|
24-Feb-24 |
by Kim McDowell |
Two more bikes and helmets were given out on Friday February 23 at Westside Elementary school.
|
6-Jun-24 |
by Kim McDowell |
We completed bike giveaways to Parkside Elementary School (two bikes) and Clark Elementary school (one bike) on May 31, 2024 which was the last day of school before summer break. We should finalize the Summer reading program bike give away by the end of September.
|
14-Oct-24 |
by Kim McDowell |
Purchased three bikes and helmets on May 23 at a cost of $350.28 for Parkside and Clark Elementary Schools. Gave away on May 24, 2024.Purchased two bikes and helmets on August 15 at a cost of $315.93 for Park County Library summer reading program. Made final bike purchase for summer reading project on September 20, 2024 for four bikes and helmets for Southside and Westside Elementary Schools. Gave away September 24, 2024, to wrap up our Rotary Reading for Bikes program. Total spent for project was $2063.36. Project is now complete.
|
14-Oct-24 |
by Randall Looper |
Kim,
I do not see the final report or the receipts from this grant. Can you look to make sure you can see those items in the documents area and let me know.
Randy
|
14-Oct-24 |
by Kim McDowell |
System Entry: Project has been implemented and final report uploaded.
|
21-Oct-24 |
by Kim McDowell |
10/21/24 added final grant summary details.
|
21-Oct-24 |
by Randall Looper |
Kim,
Thanks for doing the summary but you need to complete a District report as well. The District grant report form can be found at the following link.
https://www.rotary5440.org/page/district-amp-global-grants
Open the link and at the bottom of the page under District Grant Links you will find the grant report form. Download it complete it and sign it. Than upload the signed copy to the documents area.
If you have any questions please let me know.
Randy
|
24-Oct-24 |
by Kim McDowell |
Submitted District Grant Final report 10/24/24
|
24-Oct-24 |
by Randall Looper |
System Entry: Final report approved by the District Approval Committee.
|