21-May-15 |
System Entry |
Creation of project page.
|
21-May-15 |
System Entry |
Project sent for club signatures.
|
21-May-15 |
System Entry |
Project signed by Mahmoud El Guindy.
|
15-Jun-15 |
System Entry |
Project signed by George Wilson.
|
26-Jul-15 |
System Entry |
Project approved by the District Approval Committee.
|
13-Aug-15 |
System Entry |
Check for DDF payment issued by Foundation Treasurer.
|
2-Mar-16 |
by Mahmoud El Guindy |
The Sea Base visits by the selected 3 schools have been completed. Bills for Sea Base have been paid. Awaiting transportation billing to finalize and post.
|
21-Apr-16 |
by Mahmoud El Guindy |
Added Photos and document from Sea Base.
Added Paid Bills from Sea Base
|
2-May-16 |
System Entry |
Project has been implemented and final report uploaded.
|
4-May-16 |
System Entry |
Final report approved by the District Approval Committee.
|