Project Description

Region: Asia

Country: India

Location: Shegaon

Total Budget: $39,760

Area of Focus: Water, sanitation and hygiene



CLUB ID: 87696, ROTARY DISTRICT: RI 3030

REGD OFFICE: SHRIRAM ESTATE PREMISES, MAIN ROAD, SHEGAON - 444203, DIST - BULDHANA,

MAHARASHTRA

______________________________________________________________________________________________________

GLOBAL GRANT PROJECT PROPOSAL

By - Rotary Club of Shegaon (Club ID 87696)

Project Name

Widening & Deepening of 2 kms of Unad Naala at Yeulkhed

Unad Nala carries the unabsorbed surface water of Shegaon City as well as sewerage of Shegaon City

to some extent. This Nala flows from Shegaon to Kalkhed to Yeulkhed and finally merges into bigger

Nala (which comes from Khamgaon), which finally merge in Purna River.

Geographical Location

Yeulkhed is located in Taluka Shegaon, District Buldhana, Maharashtra. It is situated approx. 12 kms

from Shegaon Railway Station. Google Location of proposed site is 20.879986354091663,

76.65252570875955

Soil, Climatic & Socio Economic Condition of the Proposed Site

The site falls under draught affected Vidarbha Region with serious history of farmer suicides and

known for acute water scarcity. This is also industrially backward district of Maharashtra and

economic condition of the surrounding villages is heavily dependent on non irrigated agriculture. So,

people generally take 1 crop or max 2 crops with high risk of failure of 2nd crop.

Average Rainfall is 931 mm annual. Temp ranges from 13 Deg Celsius in winter to 47 Degree Celsius

in Summer. Bore water is generally available at depths of 400-600 ft with High TDS of upto 3000.

The area is blessed with rich BLACK SOIL upto 15 - 25 feet and below that there is "Chopan" soil

which doesn't allow percolation of water. In the Unad Nala, this Chopan Soil is available at around 5

feet depth and hence this is very good for water storage.

Project Description -

Unnad Naala flows for around 4.5 kms from Kalkhed till Yeolkhed and further where it meets Farsi

Naala. Out of this 4.5 kms stretch, the self sufficient farmers, who owned land on the banks of Naala,

have already deepened around 2 kms stretch of Naala using their own resources. They are using the

water for 2nd crop and to some extent for 3rd crop as well. Widening and deepening of balance

stretch is being proposed.

We are proposing "Doh" model or similar. "Doh" Model is basically digging a pit of 300 feet length,

approx 10 feet deeper than the regular stream level and then leaving a patch of say 100 feet at the

existing depth. Such "Doh" of 300 ft length x 15 ft wide (Avg) x 10 ft deep can store upto 1260000

ltrs of water. Such 15 "Dohs" can be dug within a span of 2 kms which will store about 1.89 Crores

ltrs of water.

"Doh" will be Dug using Excavator and mud thus removed shall be carried using Tractor - Trollies to

nearby farms thereby levelling their contours and avoiding flooding during rainy seasons.

Benefits of Project -

1. Storage capacity of Water around 1.89 Crore Ltr - Water will be used for irrigation and cattle

feeding

2. As the source of water includes unabsorbed water from Shegaon City as well as sewerage of

Shegaon City, water flows in Unad for almost upto the month of April beginning. So, the

storage is expected to be replenished multiple times - thereby better utilization of created

storage facility.

3. Levelling of nearby fields - better yields due to silt and lesser loss during rainy season

flooding

4. Sure improvement in yields of Rabi Crops of beneficiary farmers & possibility of 3rd crop for

some of them

Quantum of Benefit

Population of Yeulkhed as per 2011 Census was 955 (233 families). This size is expected to be around

1100 as on date. Approx 80 farmers have their farms on the banks of Unad. Thus, the number of

direct beneficiaries will be around 400.

In addition, indirect beneficiaries like neighbouring farmers, cattle, birds, etc will also be benefitted.

Farmers who receive the silt will be additional beneficiary.

Rotary Areas of Focus covered by this Project -

1. Water & Sanitation

Project Cost & Funding Plan -

Estimated costs are as follows -

1. Excavator cost - Rs. 2000/- per hour x 950 Hrs = 19,00,000/-

2. Trolley Cost - 950 Hrs x 20 Trolleys/ Hr x 100/- per trolley = 19,00,000/-

3. Less: Appr 5000 Trolleys may be taken away by farmers in their own tractors = (5,00,000/-)

4. Supervision Cost by Rotary Club of Shegaon - NIL

Nett Estimated Cost of the Project = Rs. 33,00,000/-

Sources of Funds as follows -

Rotary Club of Shegaon - Rs. 9,90,000/-

Global Grant Fund (from various sources) - Rs. 23,10,000/-

Conclusion -

Rotary Club of Shegaon has arranged the donors and funds for its contribution towards this project.

As similar work has been done by some farmers on same Unad Nala, the experience of those

farmers as well as confidence of beneficiary farmers is easily available for this project. This will

ensure smooth and speedy execution with full local support of the community.

Considering above points i.es financial resource mobilization by the club and surety of proper

execution, Rotary International and Rotary Dist 3030 are kindly requested to take this proposal for

positive consideration.

Primary Host Partner

District: 3030

Rotary Club of: Shegaon

Primary Contact: Anirudh Paldiwal

Email: anirudhpaldiwal@gmail.com

Primary International Partner

We are looking for a Club partner. Click here to pledge support for this project. Recording a pledge will make you the Primary International Partner for this project.

Project Status

Need $27,760
This project needs to receive some pledges to go to the next level. Please check the "Financing" tab to see the list of current pledges. Once the amount pledged is equal to the project budget, the status of the project will be automatically changed to "Fully Pledged".
Click here to pledge support for this project.

Project listed for the 2023-24 Rotary Year.

Proposed Financing

Existing Contributions Towards This Project

Date

Cash

DDF

Total

Shegaon (3030)

28-May-24

$5,000

$7,000

$12,000

Remaining Amount to Raise

Additional Club Contribution (Needed) - Add a contribution

$27,760

-

$27,760

Amount Requested from The Rotary Foundation (waived)

-

Total

$39,760

Note: as of July 1, 2015 there is a 5% additional support fee for cash contributions. This fee does not appear in the financials above because it does not apply if the funds are sent directly to the project account (without going through TRF, and therefore without Paul Harris credit). Clubs sending their cash contribution to TRF must be aware they will have to send an additional 5%.

Project Supporting Documents


There are no documents yet for this project.
Go to the administration page to upload documents.

Project Photos


There are no photos yet for this project.
Go to the administration page to upload photos.

History Log Entries

28-May-24

System Entry

System Entry: Creation of project page.

© 2010 Philippe Lamoise - Website design by Philippe Lamoise, D2G Online