This project is completed. Project listed for the 2009-10 Rotary Year. The Matching Grant application number from TRF is #70782. The TRF Staff in charge of this grant is Jennifer Berg (Jennifer.Berg@rotary.org).
<16-Dec-08> System Entry
Creation of project page.
<2-May-09> by Dan Gensler
Project was not sumbitted due to TRF reverting projects. This project will be submitted on July 1, 2009.
<16-May-09> by Dan Gensler
Applications updated while d-5340 team was in South Africa. Will have signed documents ready for July submission date.
<17-Jun-09> by Susan Thorning
DGSC Review complete. Please submit signature documents to DGSC for submission
<1-Jul-09> System Entry
Grant paperwork sent to The Rotary Foundation.
<24-Jul-09> System Entry
TRF Grant Number assigned: 70,782.
<29-Jul-09> by Susan Thorning
Checklist complete. Grant being forwarded for review.
<1-Sep-09> System Entry
Grant approved by The Rotary Foundation.
<1-Sep-09> by Susan Thorning
Congratulations, your grant has been approved. Documents have been sent to the two primary contacts on the grant. Please have your club presidents sign and submit your agreement, open the project account and submit your donations.
<17-Mar-10> by Ted Woodall
To date, 2 months supply of Medication aid has been delivered to Missionvale
<8-Oct-10> by Ted Woodall
Project running as planned. Expected to be completed by October 2011
<18-Apr-11> by Dan Gensler
Project is still in motion. Should be completed before the end of 2011. TRF has scheduled a trip to Missionvale to audit project in May of 2011.
<18-May-11> by Dan Gensler
Project is almost complete. TRF is doing an audit on site in the end of May, 2011.
<20-Dec-11> by Dan Gensler
This project is still in motion. We have fullfilled the original grant and petitioned TRF to allow us to use the funds for additional medical care purposes which was approved. At the present, there is R 85,490 of remaining funds.
<16-Jul-12> by Dan Gensler
The project is still in motion but nearing the end. Ted Woodall informs me that this project should be completed in the coming months.
<14-Aug-12> by John Fistere
A report on this project needs to be submitted and accepted by TRF by 23-Aug-2012.
<23-Aug-12> System Entry
Grant status changed to "Completed".
<22-Aug-12> by Dan Gensler
Final report accepted by Stephen Copek.
|