2-Aug-22 |
by Sue Barajas |
System Entry: Creation of project page.
|
4-Aug-22 |
by Sue Barajas |
System Entry: Project sent for club signatures.
|
4-Aug-22 |
by Sue Barajas |
System Entry: Project signed by Sue Barajas.
|
4-Aug-22 |
System Entry |
System Entry: Project signed by Mike Cooper.
|
4-Aug-22 |
System Entry |
System Entry: Project signed by Dan Barajas.
|
5-Aug-22 |
System Entry |
System Entry: Project signed by Doug Clark.
|
5-Aug-22 |
System Entry |
System Entry: Project signed by Doug Clark.
|
25-Aug-22 |
by Elana Levens-Craig |
System Entry: Signature Process cancelled by user.
|
16-Dec-22 |
by Sue Barajas |
District grant funds ran out before this project could be funded and has been moved to next year. After 5, provided funds to COMPACT without the match and continues to support the youth.
|
1-Jun-23 |
by Dan Barajas |
System Entry: Project sent for club signatures.
|
1-Jun-23 |
by Dan Barajas |
System Entry: Project signed by Dan Barajas.
|
25-Jun-23 |
System Entry |
System Entry: Project signed by Sue Barajas.
|
28-Jun-23 |
System Entry |
System Entry: Project signed by Sue Barajas.
|
2-Aug-23 |
by Sue Barajas |
System Entry: Signature Process cancelled by user.
|
2-Aug-23 |
by Sue Barajas |
System Entry: Project reverted to "Published".
|
2-Aug-23 |
by Sue Barajas |
System Entry: Project is now "Fully Pledged".
|
2-Aug-23 |
by Sue Barajas |
System Entry: Project sent for club signatures.
|
2-Aug-23 |
by Sue Barajas |
System Entry: Project signed by Sue Barajas.
|
2-Aug-23 |
by Dan Barajas |
System Entry: Project signed by Dan Barajas.
|
2-Aug-23 |
System Entry |
System Entry: Project signed by Doug Clark.
|
2-Aug-23 |
by Sue Barajas |
System Entry: Project signed by Sue Barajas.
|
18-Sep-23 |
System Entry |
System Entry: Project signed by Mike Cooper.
|
19-Sep-23 |
by Alan Turner |
System Entry: Project approved by the District Approval Committee.
|
2-Nov-23 |
by Dave Brooks |
System Entry: Check for DDF payment issued by Foundation Treasurer.
|
16-May-24 |
by Sue Barajas |
Project has been completed. Report will be submitted by end of week.
|
21-May-24 |
by Sue Barajas |
System Entry: Final Report signed by Sue Barajas.
|
21-May-24 |
System Entry |
System Entry: Final Report signed by Dan Barajas.
|
21-May-24 |
System Entry |
System Entry: Final Report signed by Doug Clark.
|
22-May-24 |
System Entry |
System Entry: Final Report signed by Mike Cooper.
|
23-May-24 |
by Alan Turner |
Please provide proof of payment of the funds to Compact, or receipts, or a thank you letter.
|
23-May-24 |
by Sue Barajas |
Copy of check presentation to COMPACT was posted in photos as proof of payment.
|
23-May-24 |
by Alan Turner |
System Entry: Project reverted to "Paid".
|
30-May-24 |
by Sue Barajas |
Proof of payment to COMPACT has been uploaded as restricted document.
|
30-May-24 |
by Sue Barajas |
System Entry: Final Report signed by Sue Barajas.
|
30-May-24 |
System Entry |
System Entry: Final Report signed by Dan Barajas.
|
30-May-24 |
System Entry |
System Entry: Final Report signed by Doug Clark.
|
30-May-24 |
System Entry |
System Entry: Final Report signed by Mike Cooper.
|
31-May-24 |
by Alan Turner |
System Entry: Final report approved by the District Approval Committee.
|
29-Jun-24 |
System Entry |
System Entry: Final Report signed by Dan Barajas.
|
30-Jun-24 |
by Alan Turner |
System Entry: Final report approved by the District Approval Committee.
|